×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Use of existing concrete ground slab as foundation

Use of existing concrete ground slab as foundation

Use of existing concrete ground slab as foundation

(OP)
I am working in project in which the project is a fast track. The project involves refurbishment works in which some 230mm thick masonry walls 6m high need to be constructed on the existing concrete ground slab. There are no as built drawings for the existing building. I am thinking of designing aa raft foundation to be constructed on this existing slab. And the wall to be a cellular masonry wall free standing to 6m above the proposed slab. Any advise?

RE: Use of existing concrete ground slab as foundation

You need to know what the subsurface conditions are under the existing slab, in other words get geotech advice.  Drilling through the slab for your borings will give you the ground slab thickness.

What provides out of plane strength for these 6 metre high walls?  As you say they are 230 thick, I assume that means double brick.  Reinforced vertically and braced at top?

When you say a "raft foundation", do you mean a spread footing cast on top of the slab?

When you say the project is "fast track", remember the old adage:  You may want it done fast, cheap, and right, but you can only have two of the three.


RE: Use of existing concrete ground slab as foundation

In some older buildings that we have dealt with there has been some localized (and sometimes substantial) settlement of the original grade below the slab.  The older the building, the more suspect, IMHO.  They haven't always had vibratory plate compactors.  Though not intended to, the slab on grade then ends up with voids and pockets below as it spans over these hollow spots.  Usually fine with foot or light wheel traffic, but put a wall or new column on it and it can give you trouble.

Beyond the other issues, I'd carry some exploratory holes and injection grouting if necessary before I'd set a new wall on an existing slab.

.02

 

RE: Use of existing concrete ground slab as foundation

Chedim,

I assume you are in Australia due to the references to 230mm wall and raft slab.

I have actually seen slabs on ground where they never even bothered to remove the grass. Your job as a structural engineer is not to make assumptions (e.g. that the existing slab on ground is okay) your job is to make sure that things are okay in a scientific and thorough manner. Get a boring done, they are very cheap compared to the consequences.

If you do end up using the existing slab then put 50mm of sand blinding between it and the new footing to minimise shrinkage restraint from friction.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources