INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Mine Grounding M421

Mine Grounding M421

Mine Grounding M421

(OP)
Hi All,

 M421 from CSA, Mining electricity code in canada is not that helpful in clarifying grounding grid design for underground mines. It talks about a GPR of 100 V.

As per MSHA, it is required to have a Safety grid and a substation ground. The three conductors Phase A, B and C come from the substation but the ground comes from another ground grid located more than 25 away from the substation ground. So, that any ground potential rise due to a fault in substation should not creat a rise in potential at the mine ground underground.

Could you kindly advise, if this is how mine grounding is done ?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources