Duration problem
Duration problem
(OP)
When I write in a duration of 5 days I get dates from monday to monday next week. That's fine. When I do the same for 10 days I get to tuesday the following week and so on to wednesday for 15 days. Same applies if I use 1 week or 2 weeks.
There are no extra free days in between, using a standard calendar. I am using a norwegian version (Project 2003).
Why is this happening. I thought a week was 5 days (working).
There are no extra free days in between, using a standard calendar. I am using a norwegian version (Project 2003).
Why is this happening. I thought a week was 5 days (working).
Cheers. Sean.





RE: Duration problem
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Duration problem
However when I create a new calendar I can't get it to give me everyday set to 8 - 17 as default (with weekends off), even though that is the default in Options - and that is using Project 2003 at home - English version.
How do I get a proper default set up? (simple questions I know)
Cheers. Sean.
RE: Duration problem
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
RE: Duration problem
Thanks for the help.
Cheers. Sean.