Actual Finish and Physical % Complete
Actual Finish and Physical % Complete
(OP)
MS Project automatically sets the value for Actual Finish when '% Complete' becomes 100%. Is there a way to change it so that Actual Finish value will be set when 'Physical % Complete' becomes 100%?