INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Point of Fixity of a Pile or Drilled Shaft

Point of Fixity of a Pile or Drilled Shaft

Point of Fixity of a Pile or Drilled Shaft

(OP)
I am working on an analysis of a large Drilled Shaft and I am having trouble determining the point of fixity of the shaft. I have some texts that talk about it, but they kind of run you around in circles. The top 50 feet of the shaft is in clay. Any suggestions would be appreciated.

RE: Point of Fixity of a Pile or Drilled Shaft

Assuming the soil is uniform as depth increases and the the pier is sufficiently stiff, roughly 17 feet down.

RE: Point of Fixity of a Pile or Drilled Shaft

What are you planning on doing with the point of fixity?  When I get this question, the structural engineer is usually planning on modeling the drilled shaft as a fixed base column in a FE model, or looking at a buckling analysis.  In this case, I will perform a lateral load analysis using LPile and calculate an equivalent cantilever length.

RE: Point of Fixity of a Pile or Drilled Shaft

(OP)
I am working for the construction company that is doing the work. In the plans it states that the contractor shall provide bracing between the shafts until intil cap is placed. So I am determining the moment induced due to wind forces prior to the cap being placed.

RE: Point of Fixity of a Pile or Drilled Shaft

What is the wind blowing on and how is it attached to the drilled pile?

RE: Point of Fixity of a Pile or Drilled Shaft

(OP)
Wind is blowing on the formwork and unsolidified concrete cap.

RE: Point of Fixity of a Pile or Drilled Shaft

Drive some metal stakes around the perimeter of the formwork to resist all horizontal forces and forget about the drilled pier since it is not attached to the forms.

RE: Point of Fixity of a Pile or Drilled Shaft

(OP)
Ya, this is in a lake.

RE: Point of Fixity of a Pile or Drilled Shaft

DWHA,
A bit miserly in giving necessary information to get good suggestions.

RE: Point of Fixity of a Pile or Drilled Shaft

If I was calculating the moment in the shaft, I would use the LPile program from Ensoft.  If you dont want to (or can't) purchase the program, then the alternative would be to use the analysis method described in the NAVFAC manual.  It is available here:
http://vulcanhammer.net/download/foundations.php#dm72
Look on page 7.2-235.

RE: Point of Fixity of a Pile or Drilled Shaft

(OP)
Civilperson,
I understand that what I stated may have been a little misleading, however I did not ask for suggestions on how to brace the formwork.

Planars,
Thank you for the site, I looked at it quickly and it appears to be what I was looking for. At this time I do not have LPile, but I am going to research the program and see if I can get it. Thanks again.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources