INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Edge Loading of Concrete Wall

Edge Loading of Concrete Wall

Edge Loading of Concrete Wall

(OP)
Hello, I have an 8" stem wall which is notched out at the top 2-1/2" for joist framing. The PROBLEM is that I have a steel beam that is sitting on that 2-1/2" edge and I am not sure how to calculate the capacity of that bearing connection before you have some kind of shear slip failure toward the free face of the wall 2-1/2" in from the end of the beam.

I thought there would be some kind of shear equation analogous to "punching shear" or "shear slip" that would tell me how much I could load the 2-1/2" edge with my steel beam before a crack formed at some angle inward toward the inner face of the wall. This doesn't seem to match up though with the typical punching shear model with an outward shear path from the point load.

Is it really concrete in bearing that dictates my capacity??? What's the best way to go about this design???

RE: Edge Loading of Concrete Wall

So you have about 5 1/2" of concrete at the top of the wall correct?  Is this steel beam supporting a steel beam along exterior wall OR perpendicular?  I would put the bearing plate half on concrete and the other half on the wood and put blocking underneath. how much load are we talking about here?

RE: Edge Loading of Concrete Wall

Per AISC, you must have a steel bearing plate below that steel beam.  See page 2-141 in 9th edition ASD.  I am not sure that you going to be able to get that to work as is.

RE: Edge Loading of Concrete Wall

Edit above, this is not a requirement BUT a recomendation.  But I still question the design.

RE: Edge Loading of Concrete Wall

The PCA Notes On ACI 318 have an example using a shear friction model.  Support the beam on a plate.  Assume a diagonal crack occurs.  Tie the plate to rebar or headed studs that develop on the other side of the crack.  See shear friction in ACI 318 and that example.

RE: Edge Loading of Concrete Wall

(OP)
Thanks Vincentpa, for the direction on that.  It seems like the angle or plate with a welded bar developed into the wall is the best solution.  Section 11.7.4 definitely helps.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources