INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

% work complete recalculation on resource units change

% work complete recalculation on resource units change

% work complete recalculation on resource units change

(OP)
Hi,
 I am using MS Project 2003 and trying to do --
1.Create a new project, Add a task, set duration = 1 day
2. Change the task type to Fixed Duration and uncheck "effort driven".
3. change % Complete to 10 %.
4.Assign a resource to task. Now the diff fields will be:
    Work = 8 hrs
    Actual = 0.8 hrs
    Remaining = 7.2 hrs
    % work complete = 10%
 5. Now try to change the resource assignment units to 50%
      -- resource assignment  units does n't change
    -- Instead these fileds will change:
    Work = 4.4 hrs
    Actual = 0.8 hrs
    Remaining = 3.6 hrs
    % work complete = 18%

can anyone help me in understanding what is happening...?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources