INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Where Is Priority Coming From?

Where Is Priority Coming From?

Where Is Priority Coming From?

(OP)
Under Task Infomation/General, my tasks all seem to have a Priority of 500.    I didn't set it to that.   

- What is Priority?   
and
- Why do my tasks show 500 when I didn't specify anything?

I looked up "priority" in Help and it didn't return a topic with that in the title.

RE: Where Is Priority Coming From?

"500" is the default value.  Set the actual priority to what makes sense to you.

TygerDawg

RE: Where Is Priority Coming From?

The additional thing to know is that the Priority field setting is used to assist MS Project with automatic resource leveling.

Hope this helps!

J Black
www.pmconnection.com

RE: Where Is Priority Coming From?

(OP)
OK.  Thanks.  I see it now.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources