Question regarding tracking against multiple baselines
Question regarding tracking against multiple baselines
(OP)
Dear all,
I've seen this post:
"My first quesiton is, about baselines, when i do View, Tracking Gantt, I see the scheduled vs the Baseline, however I want to see this as scheduled vs Baseline 1 or 2 or 3...not just against Baseline, "
on the forum, but no answers were given to it.
I also have the same question; can anyone help me this one?
Thanks in advance,
Ricardo
I've seen this post:
"My first quesiton is, about baselines, when i do View, Tracking Gantt, I see the scheduled vs the Baseline, however I want to see this as scheduled vs Baseline 1 or 2 or 3...not just against Baseline, "
on the forum, but no answers were given to it.
I also have the same question; can anyone help me this one?
Thanks in advance,
Ricardo





RE: Question regarding tracking against multiple baselines
1. Right click on the Gantt Chart portion of your schedule.
2. Click on Bar Styles
3. Go to the bottom of the list
4. Type in "Baseline 1"
5. For the Appearance of the Bar Shape, select one that is very thin.
6. Under Show For, select Normal
7. Click on OK
These steps will display Baseline 1 on your Gantt Chart.
Hope this helps!
J Black
www.pmconnection.com
RE: Question regarding tracking against multiple baselines
That's exactly what I wanted. Thanks so much for your answer!
Greetings,
Ricardo