How much does the contractor really coordinate with other trades?
How much does the contractor really coordinate with other trades?
(OP)
I'm new to the HVAC business and I'm a bit curious as I'm looking over some drawings I just sent out and noticed some lighting conflicts (only 4" of clearance for some flourescent lights)
How do these types of issues get resolved?
How do these types of issues get resolved?





RE: How much does the contractor really coordinate with other trades?
In general, the contractor is likely to issue an RFI (request for information) to you, the designer, to figure out the solution. Unless it is design-build, contractors usually accept no responsibility for resolving conflicts in the bid documents. Unless they can get paid for it.
RE: How much does the contractor really coordinate with other trades?
RE: How much does the contractor really coordinate with other trades?
RE: How much does the contractor really coordinate with other trades?