INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Typical Unit Price Items

Typical Unit Price Items

Typical Unit Price Items

(OP)
I hate to ask, but I'm on short notice, does anyone have a good list of unit price line items, for typical overhead utility line construction work.  I'm trying to put together a comprehensive list of unit-priced task for a distribution construction contract, and I think I'm missing some stuff.  Thanks.

RE: Typical Unit Price Items

What are you building?

RE: Typical Unit Price Items

hello dumbo2929
yeah, what apowerengr said, you asked a vague question.  when i first started designing distribution systems, my mentor suggested that i take a supervisor from your local utliity out for lunch or dinner. if you work for a contractor or consultant i would heed the same advice.  its amazing what those older guys know and usually are more than happy to tell you what you need to learn and how to get the info.  its money well spent if youre starting out. since it seems youre on short notice i would call a city engineering dept that has done thier own utilty work.  their contracts are public documents.
i hope this helps some

RE: Typical Unit Price Items

How about Means Electrical Cost Data?

RE: Typical Unit Price Items

Means is low on overhead work, in my experience.

RE: Typical Unit Price Items

I'm guessing what the OP was asking for was a list of pricing components that go into overhead line construction and not the price of the work. Pole line contractors bid the work on unit prices with an estimated number of "units".  Final contract cost is determined by the actual type and quantity of units performed and installed. The engineers challenge is to take a design and chop it up into a reasonable number of units to minimize contract questions and extras.

The units are usually given an acronym.  "AR-4" might mean a pole anchor in rock. “GR10” is a 10 foot 2/8" ground rod, “IN-8” could be an 8 bell insulator string.

Different areas of the US have different abbreviations and descriptions and different T-Line design firms use different nomenclature.  

Some times a unit is a complete assembly like a wood H structure with all poles, cross-arms, hardware, and insulators fully assembled. Other units are small devices like "FG-2" for barbed wire fence grounding or WT for a wire tie.  Others are related to physical work like the number of trees cleared, the depth of an anchor trench or the length of a temporary access road.

This form of bidding and pricing accounts for field differences but requires a very honest contractor or very good inspection.

I don't have a good list of units. I like the idea of taking a contractor to lunch and getting a list that they are familiar with.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.