×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

AC paving at Lip of Concrete Gutter
3

AC paving at Lip of Concrete Gutter

AC paving at Lip of Concrete Gutter

(OP)
I have a client that want his contracter to "fix" the AC paving that is currently 1" above the lip of gutter. The contractor says this is ok and that they leave the AC above the gutter lip on purpose. The Greenbook only talks about a 1/8" tolerance when matching new pavement to existing pavement. The Greenbook also repeats "the pavement shall be true to grade and cross section." None of our local standards deal with this issue. Thanks for the help.

Ben
PE, San Diego

RE: AC paving at Lip of Concrete Gutter

New pavement, asphalt or concrete, should be installed to meet existing grades.  If the concrete gutter was in place prior to the asphalt being placed, then the asphalt should be installed to meet it.  The contractor is somewhat correct, in that higher is better than lower in this case; but an inch is way too much.  I would allow a quarter inch over relatively short distances, say 10 feet or so, but no more.

RE: AC paving at Lip of Concrete Gutter

Ben:

Is the contractor figuring the subgrade and base beneath the AC is going to settle and bring this down?  Unfortuantely, many pavement failures occur after the pavement section settles and becomes lower than the adjacent concrete - the water goes into the pavement base and subgrade.  Unfortuantely, the 1 inch height will ravel and crumble long before the pavement settles 3/4 inch (hopefully it does not settle that much).

RE: AC paving at Lip of Concrete Gutter

Here in Colorado Rocky Mountains, it is common for pavers to purposely leave the asphalt higher than lip of gutter.  I believe this is done for some of the same reasons listed above (settling of subgrade/basecourse and potential drainage infiltration between concrete and asphalt) and also to "protect" the lip of gutter from snow plow blades.

It does seem that a full one-inch rise is a little excessive, but, as previously stated, it is definitely better to be too high than too low.

RE: AC paving at Lip of Concrete Gutter

Your standards may not say but what does the construction specification say?  Tolerance on paving?  Check out the specifications first.

RE: AC paving at Lip of Concrete Gutter

1/8 inch above lip of gutter is correct. This allows for water to exit the pavement and enter the flow line of the gutter.

If your compaction tests for the native soil and aggregate sections meet the specified standard, i.e., 95% relative compaction, then the 1" above the concrete lip is to high. Compaction is irrelative if this was an overlay of existing asphalt.

This creates an obvious hazard to "catching your toe" and causing a fall. Liability can be an issue here.

The solution is to lower the edge of asphalt to meet the 1/8 requirement. Again, 1/8 inch is optimal, with up to 1/2 inch maybe acceptable to allow for settling of the A/C over time.

 There are propane indirect heaters that can accomplish the re-heating of the A/C in localized areas, thus making the A/C pliable again and then it's just a matter of workers raking away the excess and removing it and then re-compacting the A/C to seal it again.

The contractor probably did not figure removing asphalt into his bid, however, it seems the contractor gave you a "honest section" with the 1 inch above lip. Coring is also a quality control technique that will verify that specified standards have been met by the contractor.

RE: AC paving at Lip of Concrete Gutter

Was the contractor paid by the in place weight or volume of the AC?  If so I think he just made more money.

RE: AC paving at Lip of Concrete Gutter

What are the fix alternatives?

What credit is given for the mistake?

I'd ask for a discount of 20 percent or more for the whole paving job, followed by tack coat of the gutter, then place one inch of surface course there after compaction.

The alternative to this is rip out all asphaltic concrete and build it to specs.

Leaving it "as is" is opening up the road owner to expensive law suites.

RE: AC paving at Lip of Concrete Gutter

Do you have a city inspector?  If this is a public road they will make your client fix it. I agree with the problems of having the AC too high, but the liability will be why it is fixed.  Oldestguy has a good point if it is a private road.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources