×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Concrete Mix Design and Placement Responsibility

Concrete Mix Design and Placement Responsibility

Concrete Mix Design and Placement Responsibility

(OP)
Who is ultimately responsibile for the durability and strength of concrete?  Just the material itself, not the design of reinforced beams slabs etc.  Typically, a concrete supplier puts together a mix design and submits it to the engineer per ACI procedures for approval.  I have a contractor sending me RFI's asking if adding retarder to the mix and placing a vapor barrier below is acceptable to extend workability for a set of stairs on grade.

I feel it's the concrete suppliers responsibility to advise the contractor on something like this.  All Im concerned about is achieving the final strength and durability.

How do you typically respond?

RE: Concrete Mix Design and Placement Responsibility

The construction of the stairs is the engineer's responsibility.  Location of vapor barrier would be included in the construction of the stairs.  Allowing admixtures to an alreay approved concrete mix design should be evaluated by the engineer.

RE: Concrete Mix Design and Placement Responsibility

(OP)
Since we're not materials engineers, how does one rationalize this?  Evaluating it means we're taking responsibility for it, no?  Why take more responsibility just to benefit the contractor?

Just trying to figure out who's really responsible for what in the event there's major cracking.  I dont want anyone to turn around and say it's the engineer's fault because he approved it.

RE: Concrete Mix Design and Placement Responsibility

Ask that the contractor provide whatever documentation you require; this may include an engineering report from a third party... At the end of the day, you have to be prepared to accept this report...

Dik

RE: Concrete Mix Design and Placement Responsibility

   While the concrete supplier may give the Engineer the mix design for "no objections" - the Engineer is not buying the concrete - the contractor who is constructing the work is doing so.  In fact, I believe that the Contractor should be supplying the mix design to the Engineer - not the supplier as there is no contractual link between the two (on the vast majority of projects). The contractual arrangement is between the concrete supplier and the general contractor and the discussions between them is between them.  
   The contractor is requesting information from you as a variance to the project - the specs may not call for a retarder.  If you wish, ask the contractor to provide details as to the revision of the mix design, confirmation that the revised mix design will meet the project specifications and you may give a "no objection" or not. If the retarder is a variance to the design, you don't have to accept it.  Similarly, the vapor barrier is your call as the Design Engineer. If you are not the design engineer, then the design engineer needs to be queried.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources