INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Flare Startup

Flare Startup

Flare Startup

(OP)
Greeting to all,

Soon we will commission our new flare system. The flare is designed by a vendor namely "Zeeko". The type of seal system is the velocity seal. Currently, we have already established our own procedure for commissioning and igniting the flare header. Nonetheless, I like to know your idea or suggestions on this matter based on your experience and knowledge.

Appreciate your positive respond,
JimmyAli

RE: Flare Startup

I'd have a plan to inert the header with N2 first then when the headers have been purged, I'd inject fuel gas at the farthest which should have a perminate flow control system to gaurentee a flow, then inject fuel on the side lines to the header.

This is the outline, some varibles would be the need to sweep all side tap lines based on their volume. Also what type of ignition system the flare has would dictate what would happen if the tip got a "slug" of N2.

RE: Flare Startup

(OP)
Thanks dcasto for your super prompt respond.

Our preliminary procedure is to purge the flare with steam initially. Steam will be used since it is cheaper and available than N2. Moreover, any leaks in the flare header will be easily detectable via steam

RE: Flare Startup

If it is a new flare piping system it is ok with steam.

If it is an existing flare piping system with a new tip, for safety reasons, dcasto procedure should be followed.

RE: Flare Startup

The problem with steam is that it will condense to water and leave air behind, so you won't be able to get the air out until you heat the whole system up to over the boiling point of water. Then I would be concerned about thermal expansions with the large temperature rise.

We use N2 pump trucks to bring in 6000 gallons Liq N2 and the pump uses a pump and vaporizer.  They can run hoses all over the place to get N2 to the different branches.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources