INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Testing of Pipe/Final Weld

Testing of Pipe/Final Weld

Testing of Pipe/Final Weld

(OP)
Fellow engr's,

I'm headed to a seminar now and not able to look into the matter now.  But . . .

A power plant is replacing existing flanged steam butterfly valves with flanged gate valves of a length greater than the butterfly valves.  the system pressure/temp is 600 psig/800°F respectively.  (As such, a portion of existing piping will need be cut and removed.  Thus, there will be a new flange and perhaps a pup (short length of replacement pipe) welded to new flange prior to final installation.  The final weld testing/examination is the unknown.  Assuming the pup is from a section of pipe that has already been hydrotested, what are and where can i locate the criteria for testing/examining the final weld?  Should the pipe NOT be pre-tested and the pipe installed, then the final weld and section of piping does need to be hydrotested; thus ASME B31.1, Section 137 (Pressure Tests)applies.
Also, are there minimum lengths between welds on power plant piping (i.e. min length of pipe must be xyz-feet)?

Thanks!
-pmover

RE: Testing of Pipe/Final Weld

Quote:

what are and where can i locate the criteria for testing/examining the final weld?

ASME B31.1, Table 136.4 Mandatory Nondestructive Examination for Pressure Welds ot Attachments to Pressure Welds

For 600 psig and 800 deg F

NDT; RT or UT butt welds, greater than 2 NPS in size and VT

Quote:

Should the pipe NOT be pre-tested and the pipe installed, then the final weld and section of piping does need to be hydrotested; thus ASME B31.1, Section 137 (Pressure Tests)applies.

Have the pipe supplied in accordance with an ASME pipe specification. Hydrotesting after it is installed is NOT required. Perform NDT on all installation welds in accordance with B31.1.

Quote:

Also, are there minimum lengths between welds on power plant piping (i.e. min length of pipe must be xyz-feet)?

The axial distance between butt welds should be such that RT can be performed on only one weld at a time. Normally, I like to use 2 x PD.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources