115kV transformer sources
115kV transformer sources
(OP)
Anyone have any good leads on 115-12.47kV substation transformer sources in North America that are under a 50 week lead time right now? Word on the street is that the Katrina effect is still being felt on that market. We're looking for 30-35 weeks.






RE: 115kV transformer sources
I'd start with Virginia Transformer, then GE/Prolec, then maybe Waukesha and Delta-Star. Pauwels is certainly capable, but doubt they can meet delivery.
Caveat emptor: You should determine where core would be wound. At least one of the above could stack and wind core overseas then shop to US for tanking.
Dave
RE: 115kV transformer sources