INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

built up member weld

built up member weld

built up member weld

(OP)
I have a client that has to W8x21 beams stacked one on top of the other.  My question: is there an AISC prequalified weld I can use to attach the flanges together.  The ones shown in AISC 9th Ed. Do not show any attaching 2 plates along their edge.  The weld will only have to carry the horizontal shear (650#/inch).  I was thinking I would use a partial penetration butt weld with 0 gap since the beams are already installed.

RE: built up member weld

The joint you described is an edge joint.
You can establish a new WPS and decide which partial penetration is enough.
If there is no binding Code for your construction you are probably free to put the requirements you deem adequate.
It would be recommended however to document your procedure and the results obtained.

http://www.welding-advisers.com/

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources