INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

(OP)
As the title states:

Does a PQR for FCAW and a PQR for GTAW qualify a dual process WPS for FCAW / GTAW?

RE: Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

You mean a combined, not dual, process procedure? Yes.

RE: Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

(OP)
Cheers.

RE: Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

(OP)
If possible, for future reference, could you point me in the right direction to finding this out myself?

RE: Does a PQR for FCAW and a PQR for GTAW qualify a WPS for FCAW / GTAW

Yes.
ASME Boiler and Pressure Vessel Code, Section IX, Article 2.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources