INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Displaying only selected tasks

Displaying only selected tasks

Displaying only selected tasks

(OP)
I have written a detailed construction schedule into MS Project 2000. Now I want to display and print programs/schedules showing only the tasks relevant to the various component suppliers. Ideally just by manually selecting the required tasks. Task Filtering does not appear to let me do this. I tried assigning a material resource to one set of tasks I want to separate out, but couldn't get this to help me either. Surely it's not unusual to want to communicate subsets of the whole program to various suppliers? Am I missing something very simple?

RE: Displaying only selected tasks

You just cut and paste the required tasks into a separate file and print that out - but you may loose some relationships, thinking about it.

Or collapse sub tasks down so the printout will only have titles of sub projects on and the detail on the required bits.

Or you build your whole project with smaller indapendant 'sub project' files.

I hope this helps.

Biggy

RE: Displaying only selected tasks

Hi Mish,
Using MSP filters is fairly straightforward.
If you've assigned a resource, then just filter by that resource as follows:
On the menu bar, click the Project option / Filtered for/ using resource. This gives a dialogue box with your resource options. Select the one you're using and hey presto!
If you want to show/not show related summary tasks, you may have to compose your own filter, via Project/filtered for/more filters/new.
Good luck

RE: Displaying only selected tasks

Use the Work Break Down Structure (WBS) use codes such as zzz-yyy-xxx-www where the letters are you suppliers.

Use the filters new to set up different filters using

WBS     Contains      XXX              etc

AB

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources