INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Modifying separators?

Modifying separators?

Modifying separators?

(OP)
We are trying to developmentout plant, We have separators unit which they separate gas from crud, my question is: can we modify these separators to separate gas and water from crude?
And if we can and if we have two separators in this unit, how can we do it with continues operation(we need shutdown?), I mean the plan.

RE: Modifying separators?

Dear ProEngr,
Give more details:
1. Are the two separators in series or Parallel operation now?
2.Are both being used?
3.Do they have isolatiom valves on feed, Gas and crude lines?
4.Can you afford to reduce the production rate by half?
5. If the answer to all these questions are YES then by now you should have guessed the right answer to your posting!!!
Best wishes

RE: Modifying separators?

You can add weirs to the internal of the separators.  If they are horizontal, you can add a water boot with weirs.  There are several designs for internals, the best arrangment is basde on ratio of oil/water/and gas.

RE: Modifying separators?

(OP)
Hi reena1957,
the two separators are in series and both used, but I can’t understood  you in 3rd & 4th question?

RE: Modifying separators?

(OP)
Hi dcasto,
The two separators are horizontal, please how can we add boot weirs, I mean the plan, what we need?
The flowrate 100,000 bbl/day with 50%water.
Thank you.

RE: Modifying separators?

close isolation valves or shut unit down
cut hole in drum
weld boot on
open isolation valves or start unit up

RE: Modifying separators?

At 50% water, you will not need a boot. You'll need a weir about 1/2 the diameter located about 2/3 the way downstream of the vessel lenght (in the direction of flow.  The water draw shoud be about 50% of the way along the lenght off the bottom.  The oil draw about 90% of the way down the lenght, on the bottom.  The gas would be about 50% the lenght on the top.  Taps will also have to be put on the vessel to mount vevel controlers/transmitters.

These are approximate, A vessel engineer should be called in to verify the capacity of your system and how to arrange the weiers and level taps.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.