INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Groundwater w 10 ft. head vs. 2 ft. 150 psi wet concrete

Groundwater w 10 ft. head vs. 2 ft. 150 psi wet concrete

Groundwater w 10 ft. head vs. 2 ft. 150 psi wet concrete

(OP)
It seems using basic principals of pressure that if I have a leak in a concrete form allowing groundwater with 10 feet of head behind it (excuse my layman wording)to seep in, that pouring (a wet) two foot thick slab into the form would fill the hole but never stop the intrusion of water.

We have a tunnel floor patch to do where we don't want to drill wells around the perimeter to intercept the ground water.  If I try to push a two foot thick concrete pour ((150 lb./cf)(sqft/144sqin)(2ft)= 2.08 psi) against groundwater intruding ((62.4 lb/cuft)(10 ft of head)(sqft/144 sqin)= 4.3psi), it seems that though the concrete will resist the water, the water will still percolate up the sides while the concrete is wet and curing, and will continue to intrude.

We plan to use a water activated grout (De-neef foam) in the bottom corners injected through tubes from above after, but I am worried water will still sneak by because the water may snake some new path into the pour.

Any ideas or advice would be great.  Thanks     

RE: Groundwater w 10 ft. head vs. 2 ft. 150 psi wet concrete

Inject the grout first, all around the hole. you also could use some installed weep pipes. Place pipes around the patch area and connect them to a pump to remove more of the water. this should give you enogh time for the patch to cure. then cut and seal the pipes

Richard A. Cornelius, P.E.
WWW.amlinereast.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources