INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

GMAW Welding for B31.3
2

GMAW Welding for B31.3

GMAW Welding for B31.3

(OP)
Can anyone comment on whether or not if GMAW welding is permitted for use in B31.3?  Our company has WPS & PQR (for P#1 and P#8) on file approved for ASME Section IX.  The WPS and PQR was approved by a CWI.

RE: GMAW Welding for B31.3

B31.3 references the requirements of Section IX and does not prohibit GMAW.  Your Section IX procedures should be OK as long as the qualified joint designs and other essential variables meet the requirements of the B31.3 application, you have good confidence in the current skill level of the welders with the specific GMAW procedure, and you have selected the appropriate NDE methods relative to the types of weld flaws that may be present and the service requirements

RE: GMAW Welding for B31.3

GMAW, properly qualified, would be fine after the root.  As a root pass it might be a little more troublesome to get sound manual welds that pass RT.  But it is done- some automatic "robotic" pipe welding machines use GMAW for the entire weld.

RE: GMAW Welding for B31.3

GMAW has a dark cloud over it because there are four possible modes of metal transfer, each with different operating characteristics.

ASME Section IX has certain restrictions on the short circuitig mode of metal transfer that limits the thickness range for which you are qualified.

Short circuiting transfer produces rather limited heat input, thus prone to fusion type discontinuities unless the welder is properly trained and close attention to cleaning, joint preparation, and welding parameters are controlled.

The contractor must be aware of the limitations and which mode of metal transfer is being used.

Best regards - Al

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources