INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Continuous Footing Under Pile-Supported Wall?

Continuous Footing Under Pile-Supported Wall?

Continuous Footing Under Pile-Supported Wall?

(OP)
This is a survey:  Do you show a continuous footing or mud slab or nothing below c.i.p. basement walls that span between deep foundations?  Do you put a note on the drawings that slab-on-grade adjacent to bottom of wall must be in place prior to back-filling behind the wall?

RE: Continuous Footing Under Pile-Supported Wall?

If the wall is designed to span between piles, similar to a tilt wall, there is no reason you have to have a footing.  Just make sure the bottom of the wall is deep enough below fin. grade.

If the stability of the wall is dependant on the slab, then it must be installed before backfilling.  If support at the top of the wall is requried, then the floor has to be installed also before backfilling.  

In this situation, I prefer to pour the piles, then a grade beam (which is designed to span the piles) monolithically with the slab, then the wall.  So this way the wall doesn't have to span the piles.

RE: Continuous Footing Under Pile-Supported Wall?

Sometimes use a void form between piles.  When the contractor forms the wall, the forms just go to grade, supported by stakes and gravel bedding and the gravel extends to the face of the form to keep the concrete from leaking out.  I've never seen a mud slab or footing used... only time footings are in place is an existing condition and the wall is underpinned using piles

I use a note that the contractor is to provide for lateral support at the top and bot of the wall prior to backfilling against the wall.

Dik

RE: Continuous Footing Under Pile-Supported Wall?

I would have a grade beam across the top of the piles.  It may be cast integrally with the wall.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources