INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Enlarge existing footing??

Enlarge existing footing??

Enlarge existing footing??

(OP)
Has anyone enlarged an existing concrete spread footing by doweling reinforcing into the sides and pouring a larger footing around the 4 edges of the existing? (adding floors to existing building)

Not my idea, I would like to remove the existing and build a new footing. The builder suggested this to save shoring costs and minimize disruption to on-going operation at the footing level.

The Owner of course thought this was a wonderful idea!

I'm cross posting to structural also.

RE: Enlarge existing footing??

I've done this with major bridge footings that would impact traffic if we had to remove them and the supporting columns/beams.  

Building footings seem smaller and more redundant such that doweling is too labor intensive (read time consuming) and expensive.

Regards,
Qshake

Eng-Tips Forums:Real Solutions for Real Problems Really Quick.

RE: Enlarge existing footing??

yes, but also by providing a 6" or 8" bit of the footing underneath the existing footing, dowelling it using Hilti Hit and using 'wrap around' rebar in the square 'annular' ring.

Dik

RE: Enlarge existing footing??

Caltrans (California DOT) does this quite often on its bridge seismic retrofits.  Usually the extra footing area is required to tie into the new piles or CIDH's needed.  Their detail is usually 6" - 8" split around the sides.  A splitter is used.  Dowel down with a rock drill (1" dia) at 6" o.c. then use a hydraulic splitter to break away.  Then use a demo hammer to get rid of the rest.  They dowel in rebar at a 3:1 slope and use Set45 grout.  Then, rebar all around.  They may have some information in their seismic design manual

http://caltrans-opac.ca.gov/publicat.htm

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources