INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Jacking Stresses for C-I-P bridge structures

Jacking Stresses for C-I-P bridge structures

Jacking Stresses for C-I-P bridge structures

(OP)
The Contractor has poured a bridge and the minimum concrete strengths are not being attained.  With self weight included, stresses are at capacity for this initial stage, and it appears this bridge will need to be load rated.

Do we include self weight for the jacking condition calculations?

Thanks

VOD

RE: Jacking Stresses for C-I-P bridge structures

(OP)
My post should have read, "As designed, with self weight included, stresses are at capacity for this initial stage"

VOD

RE: Jacking Stresses for C-I-P bridge structures

VOD,

When you state "stresses are at capacity" I guess you mean calculated flexural compressive and/or tensile stresses are greater than code-specified allowable stresses based upon the actual concrete strengths to date.

If so, when calculating the flexural stresses at TRANSFER, the self weight and other applicable loads present, need to be considered.

Just because the stresses exceed code-specified allowable values does NOT mean that the strength capacity is exceeded.

What concrete stresses are exceeded?

RE: Jacking Stresses for C-I-P bridge structures

VOD,

Having re-read your post, maybe you are talking about the stresses at the PT anchorages - bursting and spalling stresses due the jacking loads. If so, then you need consider only the PT jacking forces but theses areas are very non-linear areas and always contains confinement reinforcement to take care of the tensile stresses. You usually need to consider the effects of multiple anchorages and the stages that these anchorage are stressed during the jacking operation.

  

RE: Jacking Stresses for C-I-P bridge structures

(OP)
Thanks for your reply,

That's exactly what I thought with regard to flexural stresses, I was just seeing if there was another angle I could approach this from.  Fortunately for the Contractor, the concrete finally reached the design transfer strength.  We wait for the 28 day strength.

Regards

VOD

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources