INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Reinf. for circular openings in thick conc. walls.
2

Reinf. for circular openings in thick conc. walls.

Reinf. for circular openings in thick conc. walls.

(OP)
For the principal spillway of a lake, I have a concrete riser structure (8'x32' inside dims)designed using the PCA Concrete Tanks Method. I need to place a slide gate in the lower portion of the base wall that will have a 48 inch dia. thimble cast in place with the wall pour. Wall thickness is 53 inches, and steel is basic vertical/horizontal in both faces of wall, proportioned for flexure, actually min. steel controlled due to large section area.  Since the verical/horizontal bars will be stopped 3" short around the periphery of the thimble, are there any considerations I need to make such as diagonal bars at what would otherwise be four corners of the opening.  If so, what criteria should be followed.  Didn't find anything relative in ACI 318.  Thanks in advance for any advice.  

RE: Reinf. for circular openings in thick conc. walls.

Typically, you should add horizontal bars and vertical bars on each side and top and bottom of the opening.  The quantity of bars should equal the number of bars that are disrupted.  If the opening distrupts 6 bars vertical and 4 bars horizontal; place 3 additional bars on each side of the opening and 2 additional bars top and bottom.  Also, add two diagonal bars at each corner of the opening.  Extend all bars the full development length of the bar past each opening face.  If you can't achieve full development length, terminate the bar in the adacent wall with a hook.

RE: Reinf. for circular openings in thick conc. walls.

RE: Reinf. for circular openings in thick conc. walls.

(OP)
Thanks guys, hit the nail on the head.  I breezed over 13.4.2 too quickly.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources