INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

CFA Construction

CFA Construction

CFA Construction

(OP)
Does anybody know how long shoule be taken to do a pile of 1050mm (or 3-1/2ft) diameter and 14m (50ft) long by a CFA in medium dense sand and no ground water

RE: CFA Construction

About 50 minutes as an average ( 5 minutes set-up, 15 minutes drilling and 30 minutes concreting ( 4" line and concrete ))if there is no reinforcement. This is an instantaneous output ( doesn't take into account starting ops in the beginning of the shift,cleaning everything at the end of the shift, stand-by time waiting for concrete, etc ).

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources