28 day cube testing
28 day cube testing
(OP)
I work for a prestressed concrete floor manufacturer , within the Quality Department . We test 24 hour and 7 day cubes in house but all 28 day cubes are sent to an independant laboratory for testing . I was hoping that someone could tell me the necessary measures or accreditation that a company must have to test its own 28 day cubes . Is UKAS accreditation necessary , or simply machinery that is UKAS tested . Can any one help .





RE: 28 day cube testing
I would imagine that UK requirements are similar.