INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Control Joint in Concrete Curb

Control Joint in Concrete Curb

Control Joint in Concrete Curb

(OP)
I have a 32ft x 42ft pile cap foundation with a 6" x 6" wide curb all around.  The pile cap will be poured first with dowels projecting.  The curb will be poured next.  It has one #4 bar in the long direction.  My question is this:  Should I cut control joints in the curb at say 10' intervals or will the curb not crack since it is dowelled into the cap and reinforced.  I'm using f'c=4000 conc with w/c ratio=.45 and 6% air entrainment.  If I need control joints how long after the pour can/should they be cut?

RE: Control Joint in Concrete Curb

You may do better posting this in a more appropirate forum.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources