INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

SCREW CONVEYOR

SCREW CONVEYOR

SCREW CONVEYOR

(OP)
The screw conveyor is inclined at 41 degrees.It has dual shaft each 4" in dia driven by a 5hp motor 1760rpm using chain drive and face mounted. The sprockets are 17" and 8.75" dia running at 120 rpm and 60 rpm respectively. I need to change the speed of bigger sprocket to 30rpm. How big sprocket do i need?

RE: SCREW CONVEYOR

If you need to cut your speed to 1/4 its current speed, multiply the diameter by 4.  However, since you're talking sprockets, count the teeth and multiply by 4.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources