INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

steep roof puddle welds

steep roof puddle welds

steep roof puddle welds

(OP)
Are there any guidelines for puddle welds used to fasten steel deck on OWSJ steep roofs (10 rise to 7 run)?

Thanks

RE: steep roof puddle welds

Check AWS D1.3, Section 1.5.4 and Table 1.2

RE: steep roof puddle welds

(OP)
Thanks for your reply.

Unfortunately I only have the AWS D1.1, I see that D1.3 relates to sheet metal welding and requirements.  I will have to further research.  Maybe AWS D1.1 will address issue.

Again thanks.  

RE: steep roof puddle welds

Are you looking for design strength of the weld, or details and requirements for the weld, or something else?  If you want design strength of the puddle weld itself, you can calculate it using the AISI cold-formed steel code.  

RE: steep roof puddle welds

(OP)
I am looking for insight on..."AWS 1.5.4 - Arc Spot Welds… the weld is restricted to the flat position"

Maybe an alternate attachment should be used (mechanical anchor) due to steep roof slope.

RE: steep roof puddle welds

zennis...interesting definitional issue.  Welding position is usually the weld electrode relative to the piece.  In this case, since your roof slope is greater than 45 degrees, a "flat" position weld could only be done on certain features, and the deck would not be one of them.

If you are welding sheet metal, the welding and procedures should conform to AWS D1.3, Structural Welding Code-Sheet Steel.  The flat position is pre-qualified and must have a 1/32 inch concavity on the weld.  If you want to do otherwise, it would require qualifying a procedure first, then qualifying welders to that procedure.

It would be easier in this case to use mechanical fastening.

RE: steep roof puddle welds

Ron, what about arc plug welds? Ref: D1.3 Sections 1.5.6, 2.3.7 and Table 1.2

RE: steep roof puddle welds

henri2...good point.  

RE: steep roof puddle welds

If your steel decking is galvanized you have other issues too.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources