INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Task items displayed in Resource Sheets - Not working?

Task items displayed in Resource Sheets - Not working?

Task items displayed in Resource Sheets - Not working?

(OP)
Not sure if anyone has any experience with this.  Here is my senario I'm trying to transfer information from the "Gantt Chart" view to the "Resource Usage Sheet".  Specifically all of the tasks have a unique identification number used in another report ( A 5 digit number ).  Typically the managers use the Resource Usage sheet to update hours etc for each person on each project.  But they need this Unique Identification number to align things.  Right now all they can see is the project name under the resource, I cant get any other information from the Gantt View to transfer over.  Their seems to be some kind of invisible barrier.  Any help would be awesome.

RE: Task items displayed in Resource Sheets - Not working?

There are two different tables that are being used. One is a task table, the other is a resource table.  The fields are not shared between the tables.  Try this; instead of using the Resource Usage view, try the Task Usage view and then group by Resource.  You should be able to pull the unique identification number into this view.

Hope this helps!

J Black
www.pmconnection.com

RE: Task items displayed in Resource Sheets - Not working?

What you've got to understand is that where a task has a resource allocated to it Microsoft Project creates an assignment. The assignments appear in italic on the Task and Resource Usage views. If you give a Task a UIN this can be transfered to the assignment and it will then appear on both the Resource and Task Usage Views.
Will

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources