Planning Units
Planning Units
(OP)
I managed to copy the schedule from one project to another. However, it did not solve my problem.
While in the copy window generated from tools, project utilities, under "To" i changed the planning units to days from hours on the from/ original. However everything is still displayed in hours on the copied schedule.
For exmaple the Total float and the Original & Remaining Durations are all still in hours.
Originally the schedule was generated in Suretrak 3.0A. Since i converted it into P3 everything is in hours.
If anyone has a solution to the above, i would be extremely grateful.
While in the copy window generated from tools, project utilities, under "To" i changed the planning units to days from hours on the from/ original. However everything is still displayed in hours on the copied schedule.
For exmaple the Total float and the Original & Remaining Durations are all still in hours.
Originally the schedule was generated in Suretrak 3.0A. Since i converted it into P3 everything is in hours.
If anyone has a solution to the above, i would be extremely grateful.





RE: Planning Units
It appears that during the conversion all of your activities were assigned to a calendar that is in hours. You will need to either change that calendar to days or make a new calendar in days and assign each activity to that calendar.