INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Planning Units

Planning Units

Planning Units

(OP)
I have been trying to change the 'planning units' in Primavera 3.1 from hours to days. However whenever I try to change or copy from another project via the menus: tools, project utilities, copy, I consistently get a message "invalid project name", eventhough all names and characters match.

I am lost, if anyone has a solution to changing the planning units from Hours to Days. I would be very interested to know.

Thanks.

RE: Planning Units

It is dificult to change once you srart.  I suggest you make a new schedule using the correct unit, fragnet your old schedule activities, put them in the new, and use global change to adjust to the new units.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources