Tower Foundations Concrete Delivery and Pour Times
I am at the planning stage in a multi site project that is very remote and have some sites that could have 2 hour access issues. How can I control this issue?
1. Time from truck loading to pour
2. Are there methods’ to extend the delivery time and maintain a viscosity require by industry standards.
(As in winter, we use heated loads to extend the cure and set time)
I very much appreciate any input.
Edd Crosley SR
TCE, Inc
I am at the planning stage in a multi site project that is very remote and have some sites that could have 2 hour access issues. How can I control this issue?
1. Time from truck loading to pour
2. Are there methods’ to extend the delivery time and maintain a viscosity require by industry standards.
(As in winter, we use heated loads to extend the cure and set time)
I very much appreciate any input.
Edd Crosley SR
TCE, Inc






RE: Tower Foundations Concrete Delivery and pore times
RE: Tower Foundations Concrete Delivery and pore times
RE: Tower Foundations Concrete Delivery and pore times
RE: Tower Foundations Concrete Delivery and pore times
RE: Tower Foundations Concrete Delivery and pore times
RE: Tower Foundations Concrete Delivery and pore times
RE: Tower Foundations Concrete Delivery and pore times
In remote areas, the batch plants don't normally have 17 trucks available, so they can't haul it all dry and start mixing.
Check with your concrete supplier, see what their ideas are. They're bound to have run across this before.
You could possibly add some construction joints where you wouldn't normally have them as well.