I'm now pulling my hair out... I've got a tight dead-line and banging my head against the wall...!
I'm using MS Project for the 1st time. I have imputed my 36 tasks within the 24 hour period, outlining the different functions (tasks) of a distribution process from collection, packaging, distribution, returns etc...
I've got the point where setting the specific start times within the 24 hr period. I can not get the start to be anything other than the date in question.. <Task Information> - Start date - 01/09/06.. But I require more specific start times.. i.e. "Distributor travels from Hub to Manchester" 01/09/06 - 10-15hrs (for 2 hrs), for each of the 36 tasks...
Alternatively,
Can anyone suggest any other application that will be able to depict this type of information? It is only for a powerpoint presentation / handout at this stage.
Many Thanks..
A very pee'd off Mark.





RE: HELP MS Project problem - Specific Start times for tasks
To do this, go to >Tools, >Options, >View, >Date Format
Hope this helps!