INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

MS Project 2003 - Consolidated Files

MS Project 2003 - Consolidated Files

MS Project 2003 - Consolidated Files

(OP)
How do I prevent Project from linking back to a file on the LAN when working on a desk-top copy? For example, I've copied the file to my desk-top to clean resources and notes, but these changes are linked back to my original file, which I would like to leave unedited.

Thanks

RE: MS Project 2003 - Consolidated Files

Im having a mojor prob with recurring task
a 2 dat task 8 hrs a day - when set as recurring task with resource on 4 hrs a day - shows duration of 1.5 days instead of 1 - help pls

this is just a sample - im trying to get someone in for meetings only - so recurring task and the duration is way out but if i can solve this sample i think i can get there

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources