engineering piping man hour estimation
engineering piping man hour estimation
(OP)
In PIPING ENGG. Varies doc.to be issued.
How to calculate Piping Man-hrs?
How much man-hours to be taken per line as Engg. Std?
If we have one project contains 200 lines (2" to 20") and we consider following activities.
1. From feed study to develop final studies
2. And upto final construction layout and isometrics
If anyone having information please reply
Jacobson
Piper.group@yahoo.com
How to calculate Piping Man-hrs?
How much man-hours to be taken per line as Engg. Std?
If we have one project contains 200 lines (2" to 20") and we consider following activities.
1. From feed study to develop final studies
2. And upto final construction layout and isometrics
If anyone having information please reply
Jacobson
Piper.group@yahoo.com





RE: engineering piping man hour estimation
The estimations evovles a breakdown of activities, etsimation for each activity - and is dependant on the level of accuracy that you are moving in.
Try to seach for book on the subject - IMHO its to broad for this forum.
Best regards
Morten