INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

My project was postponed!

My project was postponed!

My project was postponed!

(OP)
Hi all,

My project is about a third completed and recently, <y team and I have been reallocated temporarily to a project which was in trouble. Having completed this task, we will soon return back to our project. Naturally, I would like to reflect that delay in my Gantt chart and basically move all the tasks to start from today and beyong. Because execution has already started, I can't change the start date of the project. I have tried to use a number of thing like leveling delay, but did have much success so far. When I try to level resouces everything goes back to a month ago when we switch back. I am not sure what is the best aprroach to solve this.

So my question is: What is the best way to reflect the postponing of a project during the execution phase?

RE: My project was postponed!

Hi

Fistly is your project fully networked with no danglers ?

Secondly have you baselined your Project?

Thirdly are you inputing actual start and completion dates, and then resheduling your project?

If the answer to all these is yes then when you reschedule your project the start of the ramaining chain of activities will start at the time now date.

And thus the postponement in the project will be reflected against the baseline.

If the answer is to 1 and 2 is no and yes to 3 then you can use the "Adjust Dates" Macro built into Project.

This is found by View - toolbars - Analyse (must be ticked) This then gives you the analysis toolbar.

Then click on the adjust dates button.

Adjust the date suitably.

This will only move the dates which have not started.

Hope this helps :)

RE: My project was postponed!

(OP)
Hi Blonda,

The answer is no, yes and yes.

Using your approach solved my problem quite nicely.

I thank you very much for you help! :)

Regards,

RE: My project was postponed!

No Problem,

Glad to be of Help

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources