INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Road base course water absorption

Road base course water absorption

Road base course water absorption

(OP)
Hi all,

Looking for any manual or standards dealing with recommended or required water absorption (min/max)for crushed stone for road base course for wedging method. Any numbers or values will be highly appreciated.

thanks

RE: Road base course water absorption

The standards related to moisture or water in base courses have to do with the amount of moisture at the time of compaction, to achieve appropriate compaction and stability.

The absorption is related to an aggregate property and will vary depending on your region, the aggregate source, and the gradation of the material.

In general, we do not want water to be in the base course, other than the moisture necessary for compaction at the time of placement.  It only takes a few percent by weight of moisture beyond the optimum moisture determined through moisture-density relationship testing to achieve saturation, which is to be avoided in base materials because of the inherent loss of stability that can be related to saturation.

For wedging, the gradation is important since you'll be placing a variable thickness of base material. The maximum aggregate particle size in the base material should be no more than about 1/3 of the minimum expected thickness of the material after compaction.  "Feathering" wedging courses is not a good idea.  It is better to overexcavate and install thicker base sections.

RE: Road base course water absorption

(OP)
Ron,

Thanks for the answer. I will try to keep the proposed moisture content of crushed stone within +- 2% of OMC.
I hope client will accept it. For wedging we use fraction 40-80,20-40 and 5-10mm.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources