P5 to P1
P5 to P1
(OP)
In what code book or where can I find the filler metal requirements for P5 to P1, for SMAW process. I am sure I've seen it somewhere before.
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
|
RE: P5 to P1
RE: P5 to P1
Thanks Metengr.
RE: P5 to P1
Yes, per the requirements of ASME Section IX.