INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Timeline for Testing Density

Timeline for Testing Density

Timeline for Testing Density

(OP)
Here is my situation:  Small concrete paving project.  Once the project starts, the existing concrete paving needs to be torn out and replaced quickly.  Contract says that the 6” aggregate base must be compacted to 95% Modified Proctor.  As I understand it, there are two components to measuring the in place density of the new aggregate base….The on-site portion and the laboratory portion.  

The on-site portion I understand will likely be measued by a nuclear density gauge.  No problem there.

However, an ASTM D-1557 (Modified Proctor) Moisture-Density Relationship test of a representative sample of the aggregate must be performed before the on-site portion can take place.  How do I efficiently schedule the testing lab?  Does the contractor need to stockpile his aggregate on site, then have the testing agency come out and grab a sample, spend a few days in the lab, and then start work?  Seems like a lot of waiting around to me.

So…could someone please explain the process/timeline for measuring the density of an engineered fill?  I'm trying to be as efficient as possible once construction starts, but I'm new to the soil testing game.

Thank you.

RE: Timeline for Testing Density

The lab work can be turned around in a few hours if you have a technician standing by ready to pounce, and you are starting with material that is dry of optimum so the bag sample doesn't have to be dried.  Microwave drying to get the moisture content is generally accepted and it's a whole lot faster than oven drying.  Don't know if ASTM has a standard for microwave moisture content; USBR does have one.

RE: Timeline for Testing Density

ASTM does have a standard for that. ASTM D 4643-93

What is to stop you from obtaining samples at the plant?  I am sure they are not going to crush the rock, and convey it directly to the truck.  Go to the quarry that will be the supplier, and obtain samples from stockpiles using approved ASTM methods.

Also, the plant will likely have curves for the typical stone they produce.  Ask for them, and you will see you will be shooting for.  Back that up with your own testing if you feel the need, or are required to by the project specs.  

They likely have a wealth of information on the stone at the quarry.  You can "use" the data, even if you dont trust it completely.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources