×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Slip-On welded to a reducer?

Slip-On welded to a reducer?

Slip-On welded to a reducer?

(OP)
I am looking at a drawing which shows a RFSO welded to the small end of a concentric reducer.
I do not think such a thing can be done with ASME reducers, or any other standard reducer.
What is needed is a Weld-Neck.
Is there something I am missing here?

RE: Slip-On welded to a reducer?

Are you saying the joint needs to be a butt welded connection? If the slip-on flange meets the required pipe specification, no problem.

RE: Slip-On welded to a reducer?

I think that even if you can physically fit it up & weld it, the reducer will be in the way when you try to bolt-up the flange.

RE: Slip-On welded to a reducer?

Seen it done many times. No issues with the bolts.

RE: Slip-On welded to a reducer?

It can be done, but I would not do it on piping that needs to be x-rayed and certified.  I would use an expander flange.  An expander flange is like weld end flange except it acts as a reducer. For example, a 6x4 expander flange would have a 6" weld end bore and a 4" flange bore. See attached image.

http://www.itas-no.com/itas/images/expander.jpg

RE: Slip-On welded to a reducer?

In my opinion, there is no issue around "can it be done". It can be done and as I've indicated, I've seen it done many times. For me, the issue is centered on what pipe specification applies. If the spec allows slip on flanges, the joint in question is perfectly acceptable. If the specification requires butt welded joints, obviously you would not use a slip on or socket welded joint.
You're right, you wouldn't x-ray a slip-on joint. While you can take the picture, reading the x-ray tells you almost nothing on this type of joint hence they are not typically x-rayed. If 100% x-ray is required, you can't be using a slip- on specification. Slip-on joints are typically hyrdrotested, shear waved, or liquid penetrant tested between passes.  

RE: Slip-On welded to a reducer?

Unless there's something very odd about this installation and/or space is at an unbelievable premium, just use a freakin' weld neck flange. By the time the labour to put this together is included, what possible savings can there be? Give the maintenance crew a break, and don't do this.

RE: Slip-On welded to a reducer?

I see this type of thing done all the time here in the oil fields. Normally done for space saving or just all the parts that were on hand at the time. IF these were the reasons for doing this, I say fine! BUT if they are not, then as TBP says, do it right!   ...Mark

RE: Slip-On welded to a reducer?

Don't do it.  Main reason is that 31.3 only gives you 30% of the fatigue strength/life allowance for a slip-on vs a buttweld.  Plus you can't RT the slip-on weld.  

Note that the piping codes do not consider a fillet weld to be a strength weld in the same vein as a full-pen buttweld, ergo the reduction in fatigue life allowance.

Thanks!
Pete

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources