TLE Furnace WKM & Decoke Valve Valve Operation
TLE Furnace WKM & Decoke Valve Valve Operation
(OP)
A client plans to simultaneously (USING DCS system) close one motor driven (MOV) valve (WKM valve to Pyrofrac) and at some point in time open another MOV valve (Decoke valve to Decoke, Such that pressures are balanced during the operation. What is a logical way to design this knowing the valves have different cross sectoinal areas (WKM is much larger). is therea web site that explains a methodology? This is safeguardng plan to protect from a closed outlet situation. ANy help is appreciated.





RE: TLE Furnace WKM & Decoke Valve Valve Operation
RE: TLE Furnace WKM & Decoke Valve Valve Operation