INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

PWHT

PWHT

(OP)
Is there an actual ASME code limiting the number of times I can PWHT WC6 P4 material?  Any help on this subject would be greatly appreciated.

RE: PWHT

Possibly - how is that for an ASME response?

If the application of the casting requires impact testing per a specific Code or Standard, cumulative PWHT time becomes an essential variable because this will affect impact properties.

If impact requirements are not specified, you can repair a casting as many times as necessary OR unless the purchaser has specified in the PO a limit as to the number of weld repairs.

RE: PWHT

(OP)
Thanks metengr, there is not any impact testing for this part.  Thanks again

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources