Before making changes to a schedule, I have been trying to save its original by giving it a different name by going to:
Project Utilities - Copy; and naming the Project differently under the Copy - "To" tab.
However the system responds "Invalid Project Name".
Does anyone know how to save a Schedule with a different name in P3 version 3.1, such that the original remains unchanged for later reference.
Project Utilities - Copy; and naming the Project differently under the Copy - "To" tab.
However the system responds "Invalid Project Name".
Does anyone know how to save a Schedule with a different name in P3 version 3.1, such that the original remains unchanged for later reference.





RE: Saving a Schedule
Under the "to" category. Rename the file under the heading "Project Group" If you type a name in under Project Name you'll get the error you are reporting.