INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Setting Planned Finish Date based on Remaining Work

Setting Planned Finish Date based on Remaining Work

Setting Planned Finish Date based on Remaining Work

(OP)
I am trying to use Actual Work and Remaining Work to adjust the planned Finish date of a task in progress (with an Actual Start date) when resource leveling.  However, when I level, project seems to set the planned Finish date based on the Remaining Work from the Actual Start date rather than from the current/status date.  In other words, Project seems to assume that the Remaining Work is as of the Actual Start date rather than as of the status/current date.
I thought Remaining Work calculations were based on the status (by default current) date.  Is there a setting I need to adjust so that it works that way, or am I going about this incorrectly?
Thanks in advance for your help.

RE: Setting Planned Finish Date based on Remaining Work

Have you tried baselining beforehand?

TTFN



RE: Setting Planned Finish Date based on Remaining Work

(OP)
Thanks for your reply, IRstuff.
No, I haven't yet baselined the project yet. Usually I would before work began, but in this case work on part of the project had to begin before I could confirm the plan for other modules.  I was actually doing one last resource leveling to set the planned dates based on the current status before baselining.  Would baselining first make a difference?

RE: Setting Planned Finish Date based on Remaining Work

No idea... that was the only thing I could think of that might make a difference.

TTFN



RE: Setting Planned Finish Date based on Remaining Work

I think I remember having a similar problem. Have you disabled the splitting of tasks?

RE: Setting Planned Finish Date based on Remaining Work

Under tools / options the calculation tap, there is a box to check if you want the remaining work scheduled from the status date or the actual start date.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources