Soil Improvement in Dam Foundation
Soil Improvement in Dam Foundation
(OP)
Hi,
I am searching for some case histories regarding the use of the following improvement methods in dam foundation anywhere in the world:
1- Dynamic Compaction
2- Dynamic Replacement
3- Deep Soil Mixing (as cutoff element- preferably not as a rehabilitation / remediation case)
4- Preloading (simultaneously using PVD)
5- Vibro compaction/replacement
6- Jet Grouting (both as improving the soil geotechnical parameters and as cutoff element)
7- Soil Nailing (both in the reservoir region and for any reason in the dam body region)
Regards
I am searching for some case histories regarding the use of the following improvement methods in dam foundation anywhere in the world:
1- Dynamic Compaction
2- Dynamic Replacement
3- Deep Soil Mixing (as cutoff element- preferably not as a rehabilitation / remediation case)
4- Preloading (simultaneously using PVD)
5- Vibro compaction/replacement
6- Jet Grouting (both as improving the soil geotechnical parameters and as cutoff element)
7- Soil Nailing (both in the reservoir region and for any reason in the dam body region)
Regards





RE: Soil Improvement in Dam Foundation
Penitas Dam in Mexico
Potrerillos Dam in Argentina ( liquefaction problem)
Jet grouting ( cut-off):
Thika Dam in Kenya
All these references were for new construction, not rehabilitation projects
RE: Soil Improvement in Dam Foundation
Wickiup Dam, Oregon, USA - seismic retrofit of existing dam.
Vibro Replacement (stone columns);
Lopez Dam, Arroyo Grande, California, USA - seismic retrofit of existing dam.
Regards,
Rick Hanke
Hayward Baker Inc.
www.haywardbaker.com