×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Inspection Building Pit Retaining Walls

Inspection Building Pit Retaining Walls

Inspection Building Pit Retaining Walls

(OP)
I'm designing an vehicle inspection building to check commercial vehicles.  It is a single-bay facility, 18 feet wide by 80 feet long.  The center of the bay has an inspection pit 6 feet deep by 3 feet wide, running 70 feet long to allow a person to wall underneath a vehicle to inspect the undercarriage.  There are trench drains that run along the entire length of the pit at the floor level, so the concrete floor is not tied to the walls of the inspection pit.  The design vehicle is an HS20-44.  I've designed the walls of the pit as retaining walls to withstand the soil pressure and the surcharge load of the vehicle.  Problem is, the base of the pit retaining walls works out to be 15 feet wide, since it's one slab to accomodate both walls of the pit.  I might as well extend the base to the perimeter of the building and make it a raft foundation.

Does this sound right?  I've tried to figure out a different way to design the walls of the pit so that they don't need such a huge base slab, but nothing is coming to mind.

RE: Inspection Building Pit Retaining Walls

Which floor level are the trench drains?  Pit floor or ground floor?

RE: Inspection Building Pit Retaining Walls

Since there is typically concrete placed under the trench drain, could you increase the concrete thickness under the trench drain (if needed) and tie the floor slab to the top of the pit walls?  Depending on how deep your trench drain is, this "U" shaped section of concrete around the trench drain may provide some good resistance for the wall.

RE: Inspection Building Pit Retaining Walls

(OP)
The trench drains are at ground level, thus in the way of tying the floor slab into the pit walls.

After sending in this post, I thought of looking at this differently.  Since both walls of the pit will essentially be loaded at the same time and at the same load, it's possible to design this more as a "U" shaped concrete structure resisting the moment at the center of the pit floor instead of having a huge base extending away from the pit.  Then, it's just a matter of making the pit floor slab thick enough to carry the double moment of the walls.

RE: Inspection Building Pit Retaining Walls

I would approach this like a u-shape.  Any unbalanced moment will just cause a slight rotation in the opposite wall pushing it into the soil harder and this can easily be absorbed.  (Assuming free at the top).  This will be the best design.

RE: Inspection Building Pit Retaining Walls

(OP)
aggman,
Agreed.  I've already taken that approach.  Thanks for the confirmation!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources