Smart questions
Smart answers
Smart people
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Member Login

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips now!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

Join Eng-Tips
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

LINK TO THIS FORUM!

Add Stickiness To Your Site By Linking To This Professionally Managed Technical Forum.
Just copy and paste the
code below into your site.

Partner With Us!

"Best Of Breed" Forums Add Stickiness To Your Site
Partner Button
(Download This Button Today!)

Feedback

"...I think this forum rocks it has saved my bacon many many times..."

Geography

Where in the world do Eng-Tips members come from?
MarkHerring (Petroleum)
15 Mar 06 14:55
I have my main schedule and my target schedule....how do I update the target schedule?

what im trying to do is have my main target percent complete and compare it to where the job should actually be via the target schedule

for example..I update my main schedule for march 15th...and we are showing job as being 35% complete...i then update the target schedule and it is showing we should be at 40% complete.

updating the target correctly (i.e. not making a new target date) and having it show what the target percent is.
Ibrox2003 (Nuclear)
16 Mar 06 2:54
What do you mean by updating the target schedule?  Are you adding progress to it?
MarkHerring (Petroleum)
16 Mar 06 8:24
yes...updating progress...not activities
Ibrox2003 (Nuclear)
17 Mar 06 3:06
I was always taught that adding progress to the target was a no-no.  I've never seen it done and I can't think why you would want to do it.  I'll have a play with a sample schedule and see what happens.

P3 or P3e?

Regards
MarkHerring (Petroleum)
17 Mar 06 8:32
well...how would u know where your supposed to be % wise compared to where you are on the job?

im getting asked According to the plan where SHOULD we be...and where are we ACTUALLY...(percent wise)
Ibrox2003 (Nuclear)
21 Mar 06 7:28
Mark

I wouldn't recommend updating the target.  You could do it though if you were determined to go that way.  Asuume that each target activity is progressing to schedule and then roll up Target percentage complete.  My worry is that you would inadvertently alter Target schedule dates, resources and so on.

In the past I've always produced "s" curves via a third party tool such as excel.  I've also used an EV approach with P3 to answer the "where are we v where should we be" question.

Are you using P3 or P3e?

Regards
MarkHerring (Petroleum)
21 Mar 06 7:57
I use P3

but EV will not give u a % as to where u should be.

i just heard that there is a way to take the target and update it....not changing the target dates

i know theres a way to do it...i just have to figure it out
Ibrox2003 (Nuclear)
22 Mar 06 8:05
Mark

EV will give you a % complete if you think about it.

Progressing the target project can be done either task by task or by automatically statusing activities.  The help files and P3 documentation will take you through it step by step. Keep a "clean" copy of the Target first though and on your own head be it.

Good luck.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close